CISSP · Security and Risk Management
A business continuity team is chartered to build a new BCP program from scratch. Which activity should occur FIRST?
- AConduct a Business Impact Analysis (BIA) to identify critical processes and recovery time objectives
- BDraft the crisis communication plan so executives and regulators can be notified the moment a disruption occurs
- CSelect and contract an alternate processing site so a recovery location exists before planning proceeds
- DAdd redundant power and network capacity at the primary facility to reduce the chance of disruption occurring
Show the answer
Answer: A) Conduct a Business Impact Analysis (BIA) to identify critical processes and recovery time objectives
The BIA identifies critical business functions, their maximum tolerable downtime, and recovery priorities: it must precede strategy selection (sites, technology) since those decisions depend on BIA output.